10.5.2020 22:04
Disturbances

Disturbance on Estlink 2 interconnection

Disturbance for Estlink 2 HVDC interconnection between Finland and Estonia on 10th of May 2020 at 20:56. HVDC interconnection dropped off the transmission grid. The investigation of the reason is ongoing.

Update 10.5.2020 at 23:45. EstLink 2 was back in operation at 23:06. The cause of the fault was an unjustified fire alarm. 

Additional information: Expert Jussi Huttunen phone +358 40 519 5035