Aurora Line
Project details | ||
---|---|---|
Project type: | Transmission line | |
Project state: | Building | |
Location: | Sweden, Finland | |
Length: | 380 kilometres |
Fingrid and the Swedish transmission system operator Svenska kraftnät are jointly building a new electricity transmission link between Finland and Sweden. Construction of the 380-kilometre transmission line, known as the Aurora Line, and the substations required for the project began this year in Finland.
The transmission system operator Fingrid Oyj is, in cooperation with the Swedish transmission system operator Svenska kraftnät, building a new 400 kV transmission line from Pyhänselkä in Muhos via Keminmaa to Messaure on the Swedish side of the border. Aurora Line will be commissioned in 2025. Aurora Line will increase the cross-border capacity between the countries approximately by 900 MW in the direction from Finland to Sweden and 800 MW in the direction from Sweden to Finland.
The background for the transmission line project is electricity market needs for additional capacity between Sweden and Finland. Cross-border capacity between the countries is often inadequate, which means that the electricity market cannot function efficiently and electricity prices diverge. In an import situation, this increases the price of electricity in Finland. Furthermore, the Aurora Line improves security of supply and enables integration of RES in Nordics and Baltic Sea area.
In 2016, Fingrid and Svenska kraftnät completed a study on cross-border capacity development needs. According to the report, electricity transmission connections between Finland and Sweden are inadequate and so-called bottleneck situations are very likely also in the future, so a new transmission connection is needed. Various options for increasing electricity transmission capacity were examined, and a new alternating current connection between northern Finland and northern Sweden appeared to be the most feasible in terms of the socio-economic benefit and also technically. On 23 August 2017, Fingrid and Svenska kraftnät signed an agreement concerning the realisation principles for the new connection. The new connection improves security of supply and enables integration of RES in Nordics and Baltic Sea area.
Status as Project of Common Interest
The project has been granted with Project of Common Interest status on 23.11.2017. Status can be granted to projects which are deemed essential to the integration of the European energy markets and to achieve energy policy goals of the EU. Third AC interconnection between Finland and Sweden promotes all main goals of the EU energy policy; affordable, sustainable and secure energy.
The project has been granted with Connecting Europe Facility (CEF) support of 4.325 million euros for studies. Fingrid and Svenska kraftnät will apply together CEF-funding also for the construction phase. The national energy regulators of Finland and Sweden have made Cross Border Cost Allocation (CBCA) decision on the project in March 2020.
PCI numbers and descriptions are:
4.10 Cluster Finland – Sweden [currently known as "Third interconnection Finland – Sweden"], including the following PCIs:
- 10.1 Interconnection between northern Finland and northern Sweden
- 10.2 Internal line between Keminmaa and Pyhänselkä (FI)
Aurora Line has been included into pan-European ENTSO-E Ten Year Network Development. The project has been evaluated in several occasions, most recently in 2020. The TYNDP process and identification of system needs has shown the need for the interconnector and its benefits for the region.
Learn more about Aurora Line and TYNDP
SCHEDULE |
|
Activity |
When |
Permit processes incl. environmental impact assessments |
2017 - 2022 |
Design and specification of technical solutions |
2018 - 2023 |
Bidding competitions of sub-projects and agreements |
2022-2023 |
Construction work |
2022-2025 |
Commissioning |
2025 |
Stage related info
The Environmental Impact Assesment (EIA) procedure was finalized in January 2019 for the section between Muhos and Keminmaa and between Keminmaa and the Swedish border in June 2020. Environmental studies were finalized in Sweden during 2021. Fingrid and Svenska kraftnät have agreed to fix Vuennonkoski (FI) and Risudden (SE) as the crossing point of border line.
Abstracts of EIA-reports
- Abstract of Pyhänselkä-Keminmaa 400 kV transmission line EIA-report (Finnish)
- Abstract of Keminmaa-Tornionjoki 400 kV transmission line EIA-report (Finnish)
- Environmental Impact Assesment, Keminmaa - Tornio (in Finnish)
- Environmental Impact Assesment, Pyhänselkä - Keminmaa (in Finnish)
The connection between Finland and Sweden will be implemented in two phases. At first, the section between the Pyhänselkä substation in Muhos and Keminmaa (PCI 4.10.2) will be completed. In this phase also existing Pyhänselkä substation will be expanded and a new Viitajärvi substation will be built to Keminmaa. In second phase new transmission line will be built from Viitajärvi substation to Messaure substation in Sweden (PCI 4.10.1). New line will cross the border between Finland and Sweden at Tornio-river in Vuennonkoski (FI)/Risudden (SE).
Large scale construction work started between Pyhänselkä and Viitajärvi in autumn 2022. In addition to line construction also extensions to Pyhänselkä and Messaure substations and Isovaara series compensation station will be built. In Finland also new Viitajärvi substation will be constructed in municipality of Keminmaa and new Isomaa series compensation station.
Figure 1. The planned route of the transmission line in Finland and the route alternatives being analysed in Sweden. Total length of the transmission link is about 380 km.
Keijo Välimaa
Head of Transmission Line Projects
tel. +358 30 395 5281