Grid code specifications
The Energy Authority of Finland, Energiavirasto, has confirmed Fingrid's grid code specifications for power plants and grid energy storage systems on March 20, 2025. The confirmation decision is available in the attachment section of this page.
The grid code specifications for power plants, VJV2024, and the grid code specifications for grid energy storage systems, SJV2024, come into effect immediately. The new requirements apply to all power plants and electricity storage facilities connected to Finland's electricity system with a rated power of at least 0.8 kW.
The requirements apply to new power plants and grid energy storage systems, but they also apply to existing facilities if the system technical characteristics of the facility are changed. It is the responsibility of the connection party to meet and maintain the requirements of VJV2024 and SJV2024 if the connection agreement for the power plant or electricity storage facility is made after the confirmation date of March 20, 2025, or if the facility already has a connection agreement but the binding procurement agreement is made after July 1, 2025. Otherwise, the connection party must meet and maintain the requirements that were in effect when the connection agreement for the facility was made.
General information
By virtue of the system responsibility on Finland, Fingrid has set the requirements for electrical systems and power plants connected to the Finnish power system. Whereas general principles and terms for connections are defined in Fingrid's General Connection Terms (YLE) and the of the Main Grid Contract (KVS), more detailed requirements are given in Grid Code Specifications which are presented separately for power plants, demand connections (consumption), grid energy storage systems and HVDC connections. The Terms and Specifications also apply to electrical systems and power plants connected to the customer's electricity network.
The Grid Code Specifications describe the technical and operational requirements of the equipment to be connected and the process by which the exchange of information in projects must be carried out. By complying with the requirements, we ensure that the connected equipment can withstand the voltage and frequency fluctuations caused by the power system, they do not cause interference in the power system and that they operate reliably in different operating situations and also during disturbances. The requirements also help network operators to gain access to the necessary information about the equipment.
Compliance with and verification of Grid Code Specifications is the responsibility of the Connecting Party connecting to the grid. It is important to take this into account in the agreements with suppliers. Similarly, it is advisable to start planning and exchange of information well in advance between the supplier, the related customer and the grid company, and possibly also with the distribution network company.
The current Grid Code Specifications are presented on their own pages, which also contain instructions and other background documents that complement the actual Grid Code Specification documents. The requirements are divided as follows:
- Grid Code Specifications for Power Generating Facilities, VJV
- Grid Code Specifications for Demand Connections, KJV
- Grid Code Specifications for High Voltage Direct Current Systems, HVDC
(only Finnish version available)
- Grid Code Specifications for Grid Energy Storage Systems, SJV
Previous (obsolete) Grid Code Specifications and related material can be found on the "Archive" page.
Following instructions closely related to Grid Code Specifications can be found on the Main grid contract page:
Supply of reactive power and maintenance of reactive power reserves
The document describes the requirements for reactive power reserves for power plants connected to 110 kV and 400 kV and calculation of reactive power limits applicable at the point of connection.
Real-time information exchange
The document describes the real-time measurements required to be sent to Fingrid. The measurements must be implemented before the power supply through the connection point can begin.
Details
Teemu Rissanen
Expert
tel. +358303954287
Joona Mörsky
Specialist, Power Plants
tel. 030 395 5351