Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;
6.10.2003 11:00
Press Releases

Fingrid to expand the Keminmaa substation

Fingrid Oyj, which is responsible for the national electricity transmission grid in Finland, will expand its Keminmaa substation in Northern Finland. The main contractor in the renovation project costing approx. 2.8 million euro is Fortum Service Oy. The building project will be ready towards the end of 2004.​The Keminmaa 400/110/20 kilovolt (kV) substation is an important link in the transmission connection to and from Sweden, and it also feeds electricity to AvestaPolarit Stainless Oy's Tornio steel mill. The expansion will secure electricity supply in the Tornionjokilaakso region and to mills located in the region.

The substation will have a new 400 MVA main transformer and related switchyards and secondary systems. At the same time, there will be transmission line rearrangements on the Sellee 400 kV line and on the 110 kV back-up connection. A light transfer loading station will be built for the transport of the transformer at the Laurila halt, and the road used for transporting the transformer will be improved.

The project was subjected to competition in accordance with the EU's notification rules through an open procedure. Fingrid has ordered the main transformer for the substation from ABB Oy.

Earthwork at the substation will begin next spring and actual installation work in the summer of 2004. The substation will be commissioned in stages so that the expansion will be taken into full use in November 2004. During the building work, there will be heavier than normal truck and machinery traffic in the area.

Further information: