Connection to the main grid
We implement main grid connections based on our customers need and ensure that the main grid and customer networks are compatible. We guarantee you electricity transmission capability at the connection points.
Connecting to the main grid has multiple steps. Connections are planned at the early phase in cooperation with the customer. Based on the information gathered from the customer, our experts examine customer connection possibilities and agree on the connection solution together with customer. When planning the connection solution, we take into consideration the reliability of the grid, transmission capacity, electrical safety, environmental effects as well as overall costs. Fingrid’s General Connection Terms (YLE) defines requirements for main grid connections.
During the connection planning phase, more detailed connection plans are required. Customer checks the plans with Fingrid, after which construction work can begin. Commissioning of the connection is agreed in good time with Fingrid’s operational organisation.
With up-to-date technical information exchange we ensure the best possible and technically safe result.
Planning a new connection
If you’re planning a connection to the main grid, please inform us of the necessary technical details by filling the new grid connection form.
Details
Connecting to the main grid & main grid transmission:
Petri Parviainen
Unit Manager
tel. +358 30 395 5282
Jarno Sederlund
Customer Manager
tel. +358 30 395 4251
Antero Reilander
Customer Manager
tel. +358 30 395 4199
Markus Talka
Customer Manager
tel. +358 30 395 5160
Grid code specifications:
Teemu Rissanen
Expert
tel. +358303954287
Offshore wind connections:
Laura Ihamäki
Customer Manager, offshore
tel. +358 30 395 5166