Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;

Maintaining of peak load reserve

Maintaining of peak load reserve during 1/2010-2/2011

Peak load reserve fees

0,14 €/MWh 1.-28.2.2011
0,10 €/MWh 1.11.2010-31.1.2011
0,19 €/MWh 1.1.-31.10.2010

In January and February 2010, peak load reserve capacity was activated on two days in the Elspot market in Finland and Sweden. On 8 January 2010 between 8 and 11 am, a maximum of 45 MW of peak load reserve bids were activated in Finland and a maximum of 145 MW in Sweden. The Mussalo 2 power plant in Finland was started, and it also produced some of the peak load reserve need for Sweden.

On 22 February 2010 between 9 and 12 am, a maximum of 57 MW of peak load reserve bids were activated in Finland and a maximum of 172 MW in Sweden. The full peak load reserve capacity was started in Sweden, but no peak load reserve plants were started in Finland on that day.

Maintaining of peak load reserve in 2009

Peak load reserve fees

1 January - 31 March 2009: 0.15 €/MWh
1 April - 31 October 2009: 0.18 €/MWh
1 November - 31 December 2009: 0.19 €/MWh

In December, peak load reserve bids were activated in one hour in the Elspot market in Finland and Sweden. On 17 December 2009 between 18 and 19 pm, 16.5 MW were activated in Finland and 40.5 MW were activated in Sweden. The full peak load reserve capacity was started in Sweden, but no peak load reserve plants were started in Finland on that day.

Maintaining of peak load arrangement in 2008

Peak load fees

  • generation 0.07 €/MWh
  • imports 0.40 €/MWh


In 2008, no peak load reserve capacity was activated in the Elspot market, and no peak load reserve plants were started.


Maintaining of peak load arrangement in 2007

Peak load fees

  • generation 0.07 €/MWh
  • imports 0.40 €/MWh


In February, Fingrid commissioned the starting of the Mussalo 2 power plant covered by the peak load arrangement on one occasion to secure the maintaining of power balance.