Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;

Peak load capacity 2020

December 2020

The peak load capacity costs for the grid service customers were 3,58 M€. The costs are charged according to the consumption of electricity during weekdays and during the day-time hours 7.00 a.m. - 9.00 p.m. The electricity consumption was  3 446 682 MWh, which is equal to the grid service winter weekday daytime consumption invoiced. The calculated peak load capacity fee is 1,040 €/MWh.

The peak load capacity was not started in December.

February 2020

The peak load capacity costs for the grid service customers were 4,62 M€. The costs are charged according to the consumption of electricity during weekdays and during the day-time hours 7.00 a.m. - 9.00 p.m. The electricity consumption was  2 964 187 MWh, which is equal to the grid service winter weekday daytime consumption invoiced. The calculated peak load capacity fee is 1,558 €/MWh.

The peak load capacity was not started in February.

The demand response unit Suomenoja heat pump was partly unavailable for the peak load arrangement. Also Meri-Pori power plant was partly unavailable for the peak load arrangement. Finextra reduced the compensation paid to the Suomenoja heat pump by about 3 per cent and to the Meri-Pori power plant by about 1 per cent. As defined in the  Rules of Use, the Energy Authority will make the final decisions.

January 2020

The peak load capacity costs for the grid service customers were 4,71 M€. The costs are charged according to the consumption of electricity during weekdays and during the day-time hours 7.00 a.m. - 9.00 p.m. The electricity consumption was  3 437 562 MWh, which is equal to the grid service winter weekday daytime consumption invoiced. The calculated peak load capacity fee is 1,371 €/MWh.

The peak load capacity was not started in January.