Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;
16.10.2020 13:56
Projects, Current News

Fingrid to expand the Jylkkä substation – the substation will become the most significant connecting point for wind power production in Finland

The volume of renewable energy production will grow rapidly in Finland in the coming years. Because of this, the electricity transmission system operator Fingrid has several projects underway to ensure that this new production is able to reach the distribution networks, and thus consumers, via the main grid. Fingrid’s latest contract is the expansion of the Jylkkä substation in Kalajoki and the procurement of a third transformer.

Today, 260 MW of wind power production is connected to the main grid through the Jylkkä substation. During the last couple of years, new connection agreements for wind power production amounting to 620 MW have been signed for the Jylkkä station alone. In addition, 390 MW of additional wind power production is under development in the Kalajoki and Pyhäjoki region. The volume of new wind power production to be connected is so high that it requires a significant expansion of the Jylkkä substation and the addition of a third main transformer.

The project will be completed in 2022. Once the project has been completed, the Jylkkä substation will be the most significant connecting point for wind power production in Finland.

According to the procurement decision made by Fingrid at the end of April, the expansion contract for the Jylkkä substation will be carried out by Omexom. The project will expand the current control centre building, add two fields to the 400 kV switching station and eight fields to the 110 kV switching station. In addition, the project will involve moving the westernmost 400 kV transmission line in the Finnish main grid, the so-called Coastal Line, and building a containment building for the new transformer. Expansions and improvements to the substation’s protection and control systems will also be carried out in the project.

A special feature of the project will be the implementation of the first longitudinal circuit breaker field for 110 kV busbars in the Finnish main grid, the likes of which have previously only existed for 400 kV switching stations. Longitudinal circuit breakers allow the main busbars of the 110kV switching station to be divided into up to four parts, significantly improving the availability of the substation.

The third 400/110 kV main transformer to be acquired for the substation will be supplied by Kolektor Etra. The total investment costs of the project are approximately EUR 11.4 million.

Additional information:

Project Manager Jari Tiusanen
tel. +358 30 395 5146