Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;
25.9.2019 09:00
Power System

The annual maintenance period of the HVDC connections between Finland and Sweden starts

The annual maintenance period of Fenno-Skan 1 and Fenno-Skan 2 high voltage direct current (HVDC) connections starts on Thursday 26th September. This year the target is also  to assess the remaining operational life-time of Fenno-Skan 1. The maintenance preriod ends on 3rd October. 

The annual maintenance period of the high voltage direct current (HVDC) connections Fenno-Skan 1 and Fenno-Skan between Finland and Sweden starts on Thursday 26th September. The main target of the annual maintenance is to ensure high reliability and availability of the HVDC systems.

The period starts with Fenno-Skan 2 outages, which will be finalized by Sunday evening 29th September. Fenno-Skan 1 maintenance outage starts on Saturday 28th September and lasts until Thursday evening 3rd October. The common, so called bipole outage when both Fenno-Skans are out of service is scheduled for the weekend in order to limit the impact of the unavailable crossborder capacity on electricity markets. The bipole outage is required for the maintenance work of the equipment that is common for the both Fenno-Skans.

This year the duration of Fenno-Skan 1 annual maintenance is six days which is 1-2 days longer than the usual duration of Fenno-Skan 1 outage. The need for longer outage period is due to extensive measurements and inspections which are related to the clarification project with target to assess the remaining operational life-time of Fenno-Skan 1. The project was launched in spring 2019 and its need was identified as one of the main outcomes of so called "Kvarken HVDC study", which Fingrid and Svenska kraftnät released in March 2019.

More information: 

Tuomas Rauhala, Fingrid, tuomas.rauhala[at]fingrid.fi 