Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;
30.1.2025 12:29
Current News, Power System, Press Releases

The connection of electricity consumption facilities to the main grid is temporarily tight in southern Finland

Local restrictions will apply when connecting new industrial electricity consumption facilities to the main grid in southern Finland from 2025 to 2027, after which the investments in reinforcing the main grid will be completed. The shortage of connection capacity is temporary and caused by faster than anticipated growth in electricity consumption and the decommissioning of regionally adjustable electricity production capacity in southern Finland.

 

The main grid’s connection capacity will be temporarily and locally restricted in the Uusimaa, Southwest Finland and Häme regions. The shortage of connection capacity is due to faster than anticipated growth in electricity consumption in southern Finland, coinciding with the decommissioning of regional combined heat and power production. The end of electricity imports from Russia has exacerbated the situation.

In practice, this means that from 2025 to 2027, large new electricity consumption projects may have to wait longer than normal to connect to the main grid. Limited connectivity applies to new industrial-scale demand facilities that have not yet agreed upon a connection to the grid.

The investments in reinforcing the main grid will be completed gradually and will alleviate the shortage of connection capacity. These include the construction of new transmission lines, the addition of substation transformers, and various compensation solutions to maintain the voltage of the power system. A substantial proportion of Fingrid’s €4 billion investment programme is allocated to enabling more consumption in southern Finland and facilitating the clean transition of the power system.

“Without a doubt, this is an inconvenient situation for our customers. Faster growth of electricity consumption than anticipated and the decommissioning of electricity production pose regional challenges for the transmission capacity and connectivity of the main grid,” says Jussi Jyrinsalo, Senior Vice President of Main Grid Services at Fingrid.

“Our investment programme will address this challenge in the coming years, and we will strive to facilitate as many main grid connections for customers as possible through effective cooperation,” Jyrinsalo continues.

New electricity consumption facilities offering flexible capacity and customers engaging in close cooperation with the transmission and distribution system operators can contribute to connecting new electricity consumption facilities in southern Finland. Adequate connection capacity can also be ensured by keeping regional adjustable electricity production, especially combined heat and power production, in service over the coming years.

Further information:

Jussi Jyrinsalo, Senior Vice President, Fingrid Oyj, tel. +358 30 3955118

Email addresses are in the form firstname.lastname@fingrid.fi