Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;
16.4.2025 13:34
Current News, Press Releases

Repair work on the electricity transmission link between Finland and Estonia to begin in May

The actual repair work on the EstLink 2 electricity transmission link between Finland and Estonia, which was damaged on Christmas Day 2024, will start in May. The electricity transmission link is expected to return to commercial use once the repair work is completed in July.

The actual repair work on the electricity transmission connection between Finland and Estonia will begin in May. The repair work is expected to take two months, and the connection is expected to return to commercial use on July 15, 2025. 

Preliminary work has already been carried out on the EstLink 2 submarine cable connection during February and April. The damaged section of the cable was excavated and cut out at sea for further examination, and the remaining cable sections were tested for integrity. The preliminary work aimed to reduce the risks associated with the actual repair work and helped to refine the details of the actual repair plan. 

A new cable is being installed on the seabed to replace the existing one over a distance of approximately one kilometer. Implementing such extensive repair work has required detailed planning and necessitates a specially equipped vessel for the task. The repair work has been planned and prepared since January in close cooperation with Nexans, the company carrying out the work”, says unit manager Kimmo Nepola.  
 
The cable connection will be ready to return to commercial use once the repair work is completed and the tests ensuring the functionality of the cable connection have been successfully completed. The return of the EstLink 2 connection to commercial use will be announced once the repair work is completed. 

For more information:  
Kimmo Nepola, Unit Manager, Fingrid, tel. +358 30 395 4221  
Emails are in the format firstname.lastname@fingrid.fi