Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;
26.6.2025 15:39
Current News

New conditional connection agreement model introduced to support grid connection and investment decision processes in large industrial projects

Fingrid has introduced a conditional connection agreement alongside the traditional connection agreement. This new model aims to support and facilitate grid connection and investment decision processes in large industrial projects. It will initially apply to large-scale consumption projects of at least 250 megawatts that involve long permit application processes. It is intended that the model will be developed to also cover large production projects in the future.

The energy transition poses challenges to electricity grids and there may be temporary shortages of capacity in some areas. The basic principle is that grid connection capacity will only be agreed for customer projects once their permits have entered into legal force. This will enable the efficient implementation of grid connections for projects in which the preconditions for building have been met.

However, the permit application process differs in content and duration depending on the type and size of the project in question. In order to enable and streamline large-scale consumption projects that involve long permit application processes, Fingrid has introduced a conditional connection agreement alongside traditional connection agreements. It is intended only for large industrial consumption projects of 250 MW or more, and will be further developed on the basis of the experiences gained.

A conditional connection agreement can be made once the customer has received a final conclusion report on the EIA procedure for the project, the environmental permit process has been initiated and the customer has acquired or leased the land for the project site. In addition, the network investments required for the customer connection must be feasible both technically and economically and within a reasonable timeframe. A conditional connection agreement sets out the terms and conditions for the connection of the customer's project.

It is intended that the conditional connection agreement model will be expanded in the future to cover large-scale production projects, such as offshore wind and nuclear grid connections. Fingrid is working on the application of the model to production projects together with its customers and stakeholders.