Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;
27.10.2023 09:52
Current News, Press Releases, Power System

Fingrid is investigating possible main grid connection points for offshore wind power

Interest in building offshore wind power in Finland has grown exponentially. Fingrid has launched a study to preliminarily determine possible connection points for offshore wind projects to the main grid. The results of the study are expected to be available by summer 2024.

By mid-October, Fingrid had received preliminary connection inquiries for offshore wind power projects amounting to almost 90 gigawatts. The projects are located in Finnish territorial waters, in the exclusive economic zone, and in the territorial waters of Åland. For national defence reasons, the project areas are concentrated west of Finland, north of Åland. The project areas overlap to some extent.


Locations of public offshore wind power projects and Finland's current 400-kilovolt main grid and cross-border connections.

Typically, individual offshore wind power projects are the largest power plant projects ever planned in Finland in terms of installed generation capacity. Therefore, the planning of main grid connections for offshore wind power projects requires new kinds of decentralised connection solutions and extensive system studies. Planning is particularly challenging due to uncertainty about how electricity consumption and production will develop and be located in the future. If electricity consumption will focus more on the west coast instead of the current Southern Finland, it will curb the investment needs caused by connecting offshore wind power to the main grid. If, on the other hand, the electricity produced by offshore wind power plants is expected to be transmitted to Southern Finland, several new 400-kilovolt transmission connections will have to be built in addition to the planned investments in the Finnish main grid development plan.

Fingrid has launched a study with the aim of determining possible main grid connection points and capacities for offshore wind power projects as well as preliminary schedules for implementing the connections in the 2030s. As a result of the study, main grid investments that are likely to be required for connecting offshore wind power projects will be identified, but at this stage, Fingrid will not yet make decisions on the implementation of these main grid investments or on reserving connection capacity for offshore wind power projects. The study is expected to be completed by summer 2024.

In accordance with current practice, connection capacity from the main grid is reserved for an individual project in a connection agreement, which requires that the customer has the necessary permits to build the project. For the time being, Fingrid does not have any connection agreements with offshore wind power projects. Before a connection has been agreed with Fingrid in the connection agreement, the projects' plans for connection points and connection lines must be processed as preliminary.

Fingrid is also currently considering the possibilities of developing reservation practices for connection capacity. Developers of both large electricity generation projects and consumption projects have highlighted the need to obtain certainty about main grid connections at an earlier stage than current practice to enable investment.

Further information:
Laura Ihamäki, Fingrid Oyj, tel. 030 395 5166