10.7.2023 22:58
Disturbances

Disturbance on the interconnection between Finland and Sweden

Fennoskan connections were disconnected due to a disturbance 22:05 EET. At the time of the disturbance the flow was 450 MW towards Finland.

Fault clearance has been started.