Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;
22.12.2011 15:00
Current News

Fingrid specification for the operational performance of the wind power plants has been updated

Fingrid has updated its specification for the operational performance of the wind power plant (VJV2007). The update covers the earlier wind power plants related appendices 2 and 3 of VJV2007, which has now been replaced by new appendices 2 - 6.
Considering the technical content of the VJV2007 specification, the main scope of the update is to define dedicated requirements for the wind power plants within MVA range of 0.5 - 10 MVA. The requirements specified for 0.5 - 10 MVA wind power plants are based on the requirements set for wind power plants with rating higher than 10 MVA, but the extent and level of the requirements has been modified so that the requirements reflect better the needs of connection arrangements and voltage levels that are typical for plant sizes of 0.5 - 10 MVA.
 
Additionally, in connection of the update the main content of the existing background documentation related to wind power plant requirements has been integrated as part of VJV2007 appendices. These additions are especially related to VJV2007 specification related practical implications that needs to be taken into account in wind power plant design such as the provision of the wind power plant documentation and the practices related to demonstration of the compliance. Also, a presentation covering the main items of VJV2007 specification  to be taken into account along the wind power plant project has prepared as VJV2007 background material.
 
The Fingrid specification for the operation performance of the power plants will be completely revised during year 2012 and this update basically serves as an intermediate step between the wind power plant requirements dated back to year 2008 and the 2012 revision.
 
The official material in Finnish has been released 22.12.2011:
 
 
The unofficial English translation will be made available by mid-January.
 
For further information and preliminary material in English, please contact:
 