Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;
11.2.2009 00:00

Grid plan shared by the Nordic countries and the Baltic region completed

The transmission system operators (TSOs) in the area of the Baltic Sea have drawn up a shared transmission grid plan, which examines the linking of the Baltic countries to the electricity market in the Nordic countries and Continental Europe. The plans include a new electricity transmission connection Estlink 2 between Finland and Estonia, and an interconnection between Poland and Lithuania.

TSOs in the Baltic countries, Poland, Sweden and Finland participated in the review. Interconnections from the Baltic countries to Finland, Poland and Sweden were studied. The study assessed the benefits brought by the new electricity transmission interconnections from the point of view of the electricity market. The analysis was done for several alternative scenarios, each describing a possible supply and consumption situation in the Baltic Sea region in 2025. A long-term perspective was chosen due to the long lead time of the implementation of the alternative interconnections and to the long life time of the investments.

Based on the simulated market benefits, the best solution would be to implement two interconnections, namely Finland-Estonia (Estlink 2) and Lithuania-Poland. The second best market-based alternative would be to implement the Lithuania-Poland link only. The third most viable option would be to implement both the Lithuania-Poland and Sweden-Baltic countries interconnections. The fourth best option in view of market benefits would be to build all three interconnections examined.

However, taking into account the pressing aspects of security of supply and market integration, a set of the three proposed interconnections is the most sensible solution in the long run. The execution of the three projects would mean a great leap forward in the establishment of a shared electricity grid in the area of the Baltic Sea. 

The construction of the interconnections, including the permit processes, will take several years, so the new connections will not provide immediate relief to the Baltic region. It has been decided that co-operation between the TSOs in the region will continue through security of supply analyses concerning the near future. Also, the implementation schedule of the new interconnection projects will be ascertained by the end of May 2009.

“After the summer, the work will continue in the form of Baltic Sea regional planning co-operation within ENTSO-E (European Network of Transmission System Operators – Electricity). The first European-wide ten-year network development statement of ENTSO-E will be published in 2010,” says Fingrid’s President & CEO Jukka Ruusunen. 100 million euros from the EU A new interconnection between Finland and Estonia, Estlink 2, has been proposed to receive financial assistance worth of 100 million euros from the European Union. This is part of a broader programme aiming to aid economic recovery and to promote the strategic objectives of the EU’s energy policy, such as improved security of energy supply in the Baltic countries.

The subsidy could help accelerating the schedule of the project worth some 280 million euros so that it could potentially be completed before 2015.

“So that Fingrid can make an investment decision, the Baltic states – especially Estonia – need to commit themselves to establishing a well-functioning electricity market with a credible and transparent area price. Accelerating the project schedule would mean that the schedule of market liberalisation in Estonia would have to be hastened considerably,” Jukka Ruusunen says. Further information:
Jukka Ruusunen, President & CEO, tel. +358 (0)40 593 8428
Jussi Jyrinsalo, Senior Vice President, tel. +358 (0)40 550 2044 Report: Market based analysis of interconnections between Nordic, Baltic and Poland areas in 2025