Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;

Renewal of transmission lines commenced on the Olkiluoto - Rauma line

Main grid interface reinforced at Eurajoki. Fingrid Oyj, which is responsible for the main electricity transmission grid in Finland, has launched the renewal of the 2x110 kilovolt (kV) Olkiluoto - Rauma transmission line between Olkiluoto and Junnala. This line project is part of the main grid connection arrangements required by the new nuclear power unit to be constructed at Olkiluoto.
The project, which started on 31 May through foundation work, is the first phase in reinforcing the main grid connection for Olkiluoto. Later, between 2005 and 2007, a 400 kV line will be built from Olkiluoto to Huittinen, and there will also be substations at both ends of the line.

The length of the line renewed within the current project is 10.5 kilometres, and it will be ready in January 2006. The line will run in Eurajoki from TVO’s power plant area to the separation point of the current 400 kV lines at Junnala. Existing line structures will primarily be renewed on the current right-of-way. The new line will deviate from the present route a little at Olkiluoto and in the Tahkoniemi - Junnala area, where a new 110 kV line will go under the 400 kV lines earlier than now.

The contractor in the transmission line project costing approx. 3 million euros is Empower Oy. The turn-key contract covers all engineering, construction and installation work and materials. The contract also includes replacement of some overhead ground wires on the 400 kV line between Seinäjoki and Ulvila.

Further information:
Keijo Välimaa + 358 (0)30 395 5281 or + 358 (0)40 519 5081
Project Manager

Kari Lindholm + 358 (0)30 395 5312 or + 358 (0)40 519 5084
Line Supervisor