Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Page 1 Created with Sketch. Artboard 1 copy 14Artboard 1 copy 7Artboard 1 copy 66Artboard 1 copy 23Artboard 1 copy 16Artboard 1 copy 55Artboard 1 copy 43Artboard 1 copy 50Artboard 1 copy 54Artboard 1 copy 34Artboard 1 copy 51Artboard 1 copy 36Artboard 1 copy 35Artboard 1 copy 46Artboard 1 copyArtboard 1 copy 31Artboard 1 copy 48Artboard 1 copy 9Artboard 1 copy 27Artboard 1 copy 8Artboard 1 copy 20Artboard 1 copy 2Artboard 1 copy 24Artboard 1 copy 62Artboard 1 copy 30Artboard 1 copy 41Artboard 1 copy 28Artboard 1 copy 26Artboard 1 copy 67Artboard 1 copy 52Artboard 1 copy 33Artboard 1 copy 29Artboard 1 copy 19Artboard 1 copy 53Artboard 1 copy 22Artboard 1 copy 21Artboard 1 copy 12Artboard 1 copy 13Artboard 1 copy 47Artboard 1 copy 49Artboard 1 copy 57Artboard 1 copy 32Artboard 1 copy 4Artboard 1 copy 25Artboard 1 copy 10Artboard 1 copy 15Artboard 1Artboard 1 copy 56Artboard 1 copy 11Artboard 1 copy 38Artboard 1 copy 65Artboard 1 copy 39Artboard 1 copy 5Artboard 1 copy 58Artboard 1 copy 6Artboard 1 copy 17Artboard 1 copy 40Artboard 1 copy 60Artboard 1 copy 3Artboard 1 copy 45Artboard 1 copy 18Artboard 1 copy 42Artboard 1 copy 61Artboard 1 copy 63Artboard 1 copy 64Artboard 1 copy 59Artboard 1 copy 44Artboard 1 copy 37 Combined Shape Created with Sketch. icon/info Created with Sketch. icon/info Created with Sketch. Group 17 Created with Sketch. Fill 1 Created with Sketch. Page 1 Created with Sketch. 99021DFE-DB58-4EE2-9D52-C2BF154A8B0A Created with sketchtool. Oval 2 Created with Sketch. Combined Shape Created with Sketch. Combined Shape Copy Created with Sketch. Group 18 Created with Sketch. Group 16 Created with Sketch. Page 1 Created with Sketch. ; ;
25.9.2003 00:00
Press Releases

New substation for the national grid in Eastern Finland

Substation to be built near Mikkeli will improve operational reliability. Fingrid Oyj will build a new 400/110/20 kilovolt (kV) substation at Visulahti near Mikkeli in Eastern Finland. The transformer at the substation will feed the 110 kV network in the Mikkeli region, and the substation will improve the operational reliability of the Finnish grid. The contract concerning the building work has been signed with Empower Oy.Building work at the substation site situated approx. 10 kilometres north-east of Mikkeli will begin in October. The building of a road leading to the substation area will commence before this. The new substation will have 400/110 kV transformation, 400 kV and 110 kV switchgear and a control building. The transmission lines passing the substation area will be diverted to the station, and the lines will be provided with modifications and reinforcements required by the project.

The project was subjected to competition in accordance with the EU's notification rules through an open procedure. Empower Oy will carry out the project on a turn-key basis. The contract covers engineering and building work, installations, testing and commissioning as well as purchases of all other equipment and supplies with the exception of the main transformer. The total price of the contract is approx. 4.5 million euro. Fingrid has ordered the 400 MVA main transformer for the substation from ABB Oy. The transmission line arrangements relating to the project will also be ordered separately.

The new substation will be complete in October 2004.

Further information:
Martti Heinonen, Project Manager, + 358 (0)30 395 5124 or + 358 (0)40 519 5080
Jorma Heiskanen, Regional Manager, + 358 (0)30 395 5600 or + 358 (0)400 884 411