Peak load capacity 2019

January 2019

The peak load capacity costs for the grid service customers were 4,69 M€. The costs are charged according to the consumption of electricity during weekdays and during the day-time hours 7.00 a.m. - 9.00 p.m. The electricity consumption was  3 972 801 MWh, which is equal to the grid service winter weekday daytime consumption invoiced. The calculated peak load capacity fee is 1,180 €/MWh.

The peak load capacity was not started in January. Suomenoja heat pump was partly unavailable for the peak load arrangement. Finextra reduced the compensation paid to the Suomenoja heat pump by about 9 per cent. As defined in the  Rules of Use, the Energy Authority will make the final decisions.