The preliminary transmission capacities of Fingrid between Finland and the other countries

Uppdated January 5th  2012 

The Nordic Countries (times in Finnish time)

The maximum net transfer capacity available for market is 1500 MW from North Sweden to Finland (SE1 - FI).

The maximum net transfer capacity available for market is 1100 MW from Finland to North Sweden (FI - SE1). The transmission capacity depends on power balance in the northern Finland. Typically due to winter temperatures the deficit in northern Finland increases and this will be taken into account when defining the export capacity from Finland to Sweden. During night time the export capacity may be reduced according to the forecasted deficit volume. 

The maximum net transfer capacity available for market is 1350 MW from Central Sweden to Finland (SE3 - FI).

The maximum net transfer capacity available for market is 1350 MW from Finland to Central Sweden (FI - SE3).

 

Planned changes of crossborder capacity between Finland and the Nordic Countries (year 2012) 

 

Russia (times in Finnish time)

Import to Finland (max via 400 kV connections):

Preliminary changes of Russian crossborder capacity (year 2012)