EstLink 2 (updated 28.12.2010)

Asset concerned, place: EstLink 2 between Finland and Estonia

Type if asset: HVDC interconnection, subsea cable

Effect on interconnector capacity (between control/bidding areas): capacity will increase by 650 MW to both directions

Project status: contracts, concerning the delivery of the cable and the construction of converter substations, have been signed

Estimated time of completion: early 2014.


Fenno-Skan 2 (updated 13.5.2008)

Asset concerned, place: Fenno-Skan 2 between Finland and Sweden

Type if asset: HVDC interconnection, subsea cable

Effect on interconnector capacity (between control/bidding areas): capacity will increase by 800 MW to both directions

Project status:contract agreements ready (submarine cable and converter stations)

Estimated time of completion: at the end of 2011.

EstLink 2 (updated 20.5.2010)

Asset concerned, place: EstLink 2 between Finland and Estonia

Type if asset: HVDC interconnection, subsea cable

Effect on interconnector capacity (between control/bidding areas): capacity will increase by 650 MW to both directions

Project status: investment decision done

Estimated time of completion: in the beginning of 2014. 

Fenno-Skan 2 (updated 21.2.2008)

Asset concerned, place: Fenno-Skan 2 between Finland and Sweden

Type if asset: HVDC interconnection, subsea cable

Effect on interconnector capacity (between control/bidding areas): capacity will increase by 800 MW to both directions

Project status:negotiations with manufactures continue

Estimated time of completion: November 30, 2011

 

EstLink 2 (updated 17.2.2010)

Asset concerned, place: EstLink 2 between Finland and Estonia

Type if asset: HVDC interconnection, subsea cable

Effect on interconnector capacity (between control/bidding areas): capacity will increase by 650 MW to both directions

Project status: preliminary agreement signed, no investment decision done

Estimated time of completion: at the end of 2013.