Mid-term capacity development

EstLink 2 (updated 20.12.2011)

Asset concerned, place: EstLink 2 between Finland and Estonia

Type if asset: HVDC interconnection, subsea cable

Effect on interconnector capacity (between control/bidding areas): capacity will increase by 650 MW to both directions

Project status: In manufacturing, construction and installation phase

Estimated time of completion: early 2014.
 

Fenno-Skan 2 (updated 20.12..2011)

Asset concerned, place: Fenno-Skan 2 between Finland and Sweden

Type if asset: HVDC interconnection, subsea cable

Effect on interconnector capacity (between control/bidding areas): capacity will increase by 800 MW to both directions

Project status: the project completed (submarine cable and converter stations)

Estimated time of completion: subsea cable project is completed and the capacity is available to the electricity market.


Previous reports


The size of the biggest unit in the power system will increase (updated 21.2.2008)

Asset concerned, place: commissioning of Olkiluoto 3 nuclear unit

Type if asset: Powerplant

Effect on interconnector capacity (between control/bidding areas): capacity from Sweden to Finland will decrease by 300 MW

Project status: more information www.tvo.fi

Estimated time of completion: more information www.tvo.fi